Recovery of a debt and a penalty under the construction contract.
The client (the Contractor) signed an agreement with the General Contractor to perform repair works. Later, an addendum to the agreement was signed, the subject of which was to perform additional works. The total amount of the contract was 305,282,205 rubles 42 kopecks. The Contractor presented the service acceptance acts, which were subsequently accepted by the Defendant and paid for in the amount of 303,290,495 rubles 14 kopecks. The Plaintiff presented the calculation of interest under the contract and asked the court to recover the unpaid cost of works, and a penalty under the contract.
The General Contractor did not refute the fact of the acceptance of works by the Contractor, as well as the amount of remuneration, and agreed with the calculation of interest.
The court decided to satisfy the client's claim in full and to recover from the Defendant the debt for payment of the work performed, as well as the penalty under the contract agreement.
We will help you from A to Z.
In assessing costs and risks. When deciding whether to proceed with litigation or settlement. We focus our experience and energy on building a solid foundation for relationships.